pros and cons of story points I was teaching an introductory agile training course last week and noticed that many of the students got confused about story points. Taking a step back, I can appreciate their confusion about how story points work. I personally like story points and find them helpful, especially for new teams. A lot of people don’t like them. Let’s explore why that might be.

People Get Confused About Story Points

People in my class got confused about story points. They did not seem to be confused about relative estimating. They were able to use planning poker as a team. And they did affinity estimating as a team. We used the great dog grooming exercise from David A Koontz of the Agile Complexification Inverter site. Participants were able to quickly sort the dogs into groups that were roughly the same size and would “cost” about the same for grooming. They were not confused about the concept of estimating how big things were. What seemed to throw them was specific to using story points. “Do the points equate to hours? Where do the points come from?”, and “Why do you use the Fibonacci scale?” In some cases, they thought each Fibonacci number could only be used on one item.

I Always Liked Story Points

I always thought that using story points with either story planning poker or affinity estimating were helpful, especially for new teams. I found they were both fast and accurate enough as an estimating technique. Story points support velocity calculations and that provides a mechanism for teams to gauge their consistent delivery. They also provide ways to forecast the future in what I like to call, reality-based forecasting. Using Reality-Based Forecasting in Agile Project Management - Story Points I always have discouraged teams from equating points and hours. The advantages of points wane when you make them equal to hours. And you cannot expect teams to improve their velocity if it is grounded in hours of availability. Good Scrum Masters will support the agile team to use story points correctly and prevent most of the common misuses of story points. To be clear though, story points are not part of Scrum and you won’t find mention of them in the Scrum Guide.

What Critics Say About Story Points

Critics of story points say that they get abused. Managers begin to abuse the points. They compare one team to another or question the team’s “commitment”. I’ve heard managers call teams lazy. And once someone outside the team begins to pay attention to the points, it is quite natural for the teams to begin to game the story point estimates. I would argue that the same gaming and abuse will happen with any type of estimation. Everyone that has been in the position of giving estimates knows that estimates get challenged, gamed, and abused. Other critics say that the team’s focus on points and velocity can lead to cutting corners, quality issues, and the buildup of technical debt. What do you think? This article originally appeared here and has been republished with permission